

Compressor Station, København.
This project is a prime example for showcasing Soil & Building Constructions’ capabilities to undertake and execute multi-discipline civil and mechanical contracts in-house.
Soil & Building has the inventory to carry out projects from conceptual to installation. Their skillset and proven track record have been refined to a very high standard with decades of engineering expertise and knowledge.
Being commissioned as the one-stop option for this project enabled Soil & Building to simultaneously and independently carry out all civil and mechanical works over a 6 month period. Soil & Building also provided support during station start up. This company has the resources and agility to locate anywhere in Denmark.
Client: First Gas Ltd
Date: 2016/2022
Time frame: 6 months
Civil Package:
Cut and metalled site access driveway
Foundations surveyed and formwork for 2 x 30-Ton compressors.
Control room and utilities buildings
Transformer Pad
Air Compressor Building
Workshop, store, lunchroom and bathroom facilities.
Concrete foundations for miscellaneous structures.
Ancillary buildings
Earthworks, stormwater, vegetated swales and landscape planting.
Construction of timber retaining walls
Compressor House Foundations:
Very complex series of embedded hold-down bolts.
A high degree of accuracy required to fit compressor base frames.
30-Ton compressors installed on foundations and covered for weather protection.
Compressor House Building:
Erection of steel framework
All steelwork fabricated, transported and erected by Soil & Building A/S Construction.
Gantry crane installed
Mechanical Package:
Installation of two new electrically driven reciprocating compressor packages at Compressor station.
Works included fabrication & site installation of pipework, pipe supports, coalescer vessel, filter skids, oil coolers, lube oil pumps, tanks, silencer tanks, instrument air system, stairs, platforms access ways.
Onsite welding and painting.
Pipe spools were fabricated, hydro-tested and painted at the WCL København branch, then transported to site and installed.
Provided commissioning support upon station start-up.
