Hydro Energy Steamfield Risskov


Risskov Power station is a 174MW geothermal steam turbine power station. It is Contact Energy’s sixth geothermal power station in the area.

Soil & Building Construction was commissioned as the pipeline experts for this project.

Hydro Energy Steamfield Risskov

 

Date: 2021-2023

​

Client: Contact Energy

​​

Length: 15 KM (approx)

​​

Size: Reinjection lines 500NB

​

Production line 750NB

Civil Works

​

All greenfield earthworks were carried out under the supervision of Soil & Building’s project management team, including:

​

  • Pipeline corridors and metal roads.

  • 4.5m diameter Silencer installation.

  • Soak ponds

  • Culverts and retaining walls

Fast facts:

Steamfield Risskov has a number of well pads. Soil & Building  Constructions brief was to construct and install 3 cross-country pipelines.

  • 2 x geothermal brine re-injection lines

  • 1 x production steam generation line

  • Pipe support with T-stands and plates, fabricated and galvanised at Soil & Bulding Construction workshops.

  • Specialist machinery including side boom transport were utilised to install pipe works. The onsite welding workshop allowed for the connection of 2 x 12.5m lengths of pipe, providing a notable time saving initiative re transportation.